How long does it take to fit a kitchen

How Long Does It Take To Fit a Kitchen?

A Comprehensive Guide to Timelines and Tips

One of the most common questions homeowners ask when embarking on a kitchen renovation is, “How long will it take to fit a kitchen?” The answer depends on several factors, including the size of the kitchen, the complexity of the design, the quality of materials, and whether unforeseen issues arise during the process. In this blog, we’ll break down the timeline of a typical kitchen installation, explore factors that can influence the duration, and offer tips to ensure a smooth and efficient process.

Typical Kitchen Installation Timeline

On average, a standard kitchen fitting takes 1 to 3 weeks from start to finish. However, this timeframe can vary widely depending on the specific circumstances. To better understand the timeline, let’s break the process into stages:

Planning and Design Phase

  • Duration: 2 to 8 weeks (before installation starts)

Before any work begins, the planning and design phase lays the groundwork for the project. During this stage:

    • You’ll consult with designers or kitchen fitters to finalise layouts, choose appliances, select materials, and confirm your budget.

    • Measurements of your kitchen space will be taken to ensure everything fits perfectly.

    • If custom cabinets or bespoke elements are required, they may need to be ordered, which could take several weeks to arrive.

Key Tip: Spend sufficient time in this phase to avoid delays later. Ensure your design is finalised and materials are ordered well in advance of the fitting date.

Preparation and Demolition

    • Duration: 2 to 4 days

The first on-site step in a kitchen renovation is preparing the space. This includes:

    • Removing the old kitchen (cabinets, countertops, appliances, and flooring, if applicable).

    • Disposing of waste and clearing the space for new installations.

    • Assessing the plumbing, electrical wiring, and structural conditions.

If unexpected issues are discovered, such as hidden water damage, mould, or outdated wiring, additional time may be required for repairs.

Plumbing and Electrical Work

    • Duration: 1 to 5 days

Once the space is cleared, electricians and plumbers will step in to handle any necessary adjustments:

    • Moving or installing plumbing for sinks, dishwashers, and other appliances.

    • Updating electrical outlets, lighting fixtures, or rewiring to accommodate the new layout.

    • Ensuring all systems comply with building codes.

For simple layouts, this stage may take only a day or two. More complex kitchens, such as those with island sinks or underfloor heating, may take longer.

Plastering and Wall Preparation

    • Duration: 1 to 3 days

If the kitchen walls or ceiling require plastering or re-skimming, this will happen before cabinets and appliances are installed. Plaster needs time to dry properly (usually 24 to 48 hours), which can add to the overall timeline.

Flooring Installation

    • Duration: 1 to 3 days

Some homeowners opt to replace the kitchen flooring as part of their renovation. Whether you choose tiles, laminate, vinyl, or hardwood, the installation process can typically be completed within a day or two. If underfloor heating is being installed, this could extend the timeframe.

Cabinet and Worktop Installation

    • Duration: 3 to 5 days

The installation of cabinets is one of the most critical and time-consuming stages of fitting a kitchen. It includes:

    • Positioning and securing base and wall cabinets.

    • Installing worktops (stone worktops like quartz or granite may require additional time for templating and cutting).

    • Ensuring all elements are level and aligned.

If your worktop requires bespoke cutting, the templating process (where precise measurements are taken) might take place after the cabinets are fitted. In this case, there could be a waiting period of 5 to 10 days for the worktop to be manufactured and installed.

Appliance Installation

    • Duration: 1 to 2 days

Once the cabinets and worktops are in place, appliances such as ovens, microwaves, refrigerators, dishwashers, and cooktops can be installed. This process includes:

    • Connecting appliances to plumbing and electricity.

    • Testing each appliance to ensure proper functionality.

Some appliances, like range hoods or integrated units, may take additional time to fit.

Final Touches and Finishing

    • Duration: 1 to 3 days

The final stage involves completing the smaller details that bring the kitchen together:

    • Installing backsplashes or wall tiles.

    • Adding handles, trims, and skirting boards.

    • Painting or touch-ups on walls and ceilings.

    • Conducting a final cleaning and inspection.

Once this step is complete, your kitchen will be ready for use.

Factors That Influence Kitchen Fitting Time

While the above timeline provides a general guide, several factors can influence how long it takes to fit a kitchen:

Size of the Kitchen

    • Larger kitchens naturally take more time to fit due to the increased number of cabinets, appliances, and other elements.

Complexity of the Design

    • A simple kitchen layout with standard cabinets and appliances will take less time than a bespoke design featuring custom cabinetry, integrated lighting, or intricate tile patterns.

Materials Used

    • Some materials require additional time for preparation and installation. For example:

    • Granite and quartz worktops often need templating and cutting.

    • Custom or handmade tiles may take longer to install compared to prefabricated options.

Condition of the Existing Space

    • Older kitchens may have hidden issues like outdated wiring, plumbing problems, or structural damage that need to be addressed before installation can proceed.

Availability of Tradespeople

    • If multiple trades are involved (electricians, plumbers, carpenters, etc.), coordinating schedules can sometimes cause delays.

Delays in Material Delivery

    • If materials or appliances are delayed due to supply chain issues, the project timeline may be extended.

DIY vs. Professional Installation

    • Homeowners attempting a DIY kitchen installation may take significantly longer than professional fitters due to inexperience or limited time.

Permits and Inspections

    • In some cases, you may need permits or inspections for electrical or plumbing work, which could add time to the process.

Tips to Minimise Delays

To ensure your kitchen fitting stays on track, consider the following tips:

Plan Ahead

    • Finalise your kitchen design and order materials well in advance to avoid delays caused by long lead times.

Hire Experienced Professionals

    • Skilled kitchen fitters will work more efficiently and be better equipped to handle unexpected challenges.

Communicate Clearly

    • Maintain open communication with your contractors to stay informed about progress and address any concerns promptly.

Prepare the Space

    • Clear the kitchen area of personal items and ensure tradespeople have easy access to the workspace.

Be Flexible

    • While it’s important to have a timeline, be prepared for potential delays due to unforeseen issues or weather conditions.

Opt for Standard Features

    • Choosing standard-sized cabinets and readily available materials can speed up the process compared to bespoke options.

Conclusion

Fitting a kitchen is a significant project that requires careful planning, skilled labour, and patience. While the average kitchen installation takes 1 to 3 weeks, the exact timeframe depends on various factors, such as the size and complexity of the design, the condition of the existing space, and the materials used.

By understanding the typical timeline and potential challenges, you can set realistic expectations and take steps to ensure a smooth and efficient process. Whether you’re upgrading a small galley kitchen or installing a luxurious open-plan design, the result will be well worth the effort when you finally enjoy your beautiful, functional new space.

Start the Process of Your Dream Kitchen Today!